Pinnacle Shutdown Notice
HOUSTON, April 2008 – Pinnacle will experience a shut down of its facilities in order to relocate its 20” mainline, 4” fuel line and fiber optic line due to mining operations in the area. Pinnacle will also take this opportunity to perform maintenance on its 7 ton LoCat sulfur unit. These operations will be conducted in the most expeditious manner possible, so as to minimize down time. This shut down period will also eliminate the need for an additional plant shut down in mid 2008 when the current plant expansion of the sulfur recovery system will be brought online. In that regard, the following is a schedule of events.
Saturday, April 19th – Date to shut in sour gas.
Sunday, April 20th – Date to shut in all other wells (sweet gas).
Monday, April 21st – Date to shut in Plant.
Tuesday, April 22nd – Date sweet gas expected to flow.
Saturday, April 26th – Expected return to normal operations.
Should you have any questions, please contact Angela Love at (832) 636-7118.